Banford Bridge Replacement
Timeline
Work is expected to begin in late spring / early summer and scheduled to be completed by November.
Project Details
The project includes the following:
- The removal of the existing bridge and replacement of a new bridge complete with concrete filled steel piles.
- Reconstruction of the banks of Semiault Creek.
- Restoration of the watercourse channel cross section.
- Road construction works.
- Replacement of the 600mm diameter storm main across McGuire Road.
Background Information
Banford Bridge over Semiault Creek at the intersection of Banford Road and McGuire Road is one of 23 roadway bridges in Chilliwack. This particular bridge has been previously identified in inspection reports as needing a full replacement. The preliminary design was completed in November 2021.
In 2024, the City hired ISL Engineering and Land Services to provide detailed engineering, environmental and construciton services for the bridge replacement.
Wanting to Know More?
If you have any questions about the Banford Bridge replacement, please contact the Engineering Department at 604-793-2907 or [email protected].
For email updates about transportation construction projects, subscribe to our e-newsletter.