Page 14 - City of Chilliwack 2011 Annual Minicipal Report

Basic HTML Version

2011 Concrete Works Program
• New sidewalk on Higginson from Southdowne Place to
Stevenson Road. TELUS poles required relocation for
this project.
Wheelchair Letdown on Bernard Avenue and a crosswalk
installation at Vines Street intersection.
Wastewater Treatment Plant Upgrade
Began construction of Digester #3 to improve the
hydraulic capacity and plant operation. Project cost is
$6,000,000 with completion estimated in summer 2012.
2011 Asphalt Rehabilitation
Broadway – Airport Road to Brooks Avenue
Keith Wilson Road – Boundary Road to Chadsey Road
McGrath Road – Elementary School to Camp River
McGrath Road - Nevin Road at Yale Road
Thornton Road – Promontory Road to Extrom Road
Camp River Road – Chapman Road at Standeven Road
Jesperson Road – Camp River Road to Kitchen Hall Road
School Street – Hodgins Avenue to Ontario Street
Young Road – Hocking Avenue and Southlands Drive
Vedder Road at Luckakuck Way
Progress Way - Lickman Road to Aitken Road
2011 Pedestrian Safety Improvement
Young Road at Hocking Avenue – curb radius on the
southwest corner was shortened to slow right turning
vehicles. Crosswalk was re-aligned to improve pedestrian
visibility.
The “City Hall” sign was relocated to improve pedestrian
visibility. A new meandering path will allow for a
protected pedestrian route to the intersection on the
south side of Southlands Drive.
2011 Road Safety
ICBC- funded red light camera installed at Vedder Road
and Promontory Road to cover all northbound vehicle
movement.
GPS Emergency Pre-emption system is expected to
improve First Responder response time, by anticipating
the emergency vehicle arrival time even before it is in
sight.
Back to school – The Safer City team conducted driver
awareness campaigns at 12 elementary schools in the
Chilliwack School District.
2011 Traffic Signal Program
Intersection signalization at the following locations:
Ashwell Road at Bernard Avenue
Tyson Road at South Sumas Road
Keith Wilson Road at Unsworth Road
Teskey Way at Promontory Road
Vedder River Flood Response Plan
Emergency response plan developed to identify City
actions to be taken in a high water event on the Vedder
River. The plan was presented in two public meetings
and residents were provided with information on
personal emergency preparedness.
Vedder River Management Plan Update
Process commenced for the update to the 1983 Vedder
River Management plan to incorporate new environmental
information and current understanding of the hydraulic
processes in the river.
Environmental Services Annual Programs
Household Hazardous Waste Day
Waste Reduction Week
Sustainable Business Awards
Christmas Food Drive and Shred-a-thon
Spring Pitch-In
Bailey Landfill
Management of operations at the Bailey landfill including
opening the northeast expansion area for waste,
progressive closure on the south face and installation of
new monitoring wells.
Curbside Program
Provision of solid waste and recycling collection for
over 20,000 residential customers
Engineering
2011 City of Chilliwack Annual Report
10