Successful Bidder: |
Bidder: |
Cutline Contracting |
Bid Value: |
$44,447.00 |
|
All Bidders: |
Bidder: |
Arise Contracting Inc |
Bid Value: |
$78,785.00 |
|
Bidder: |
Chilliwack Excavating Ltd |
Bid Value: |
$67,236.00 |
|
Bidder: |
Cutline Contracting |
Bid Value: |
$44,447.00 |
|
Bidder: |
Jakes Construction Ltd. |
Bid Value: |
$71,715.00 |
|
Bidder: |
Mission Contractors Ltd. |
Bid Value: |
$179,506.00 |
|
Bidder: |
Summit Earthworks Inc. |
Bid Value: |
$51,607.00 |
|
Bidder: |
Walter's Bulldozing 1994 LTD. |
Bid Value: |
$47,115.00 |
|
|
To supply all labour, materials and equipment to reconstruct the Orchard Slough Check Dam by relocating approximately 550m3 of riprap, 150m3 of granular underlay and 2230m3 of borrow general fill as stated in the Tender document. |
|
|
Frank Van Nynatten |
Project Manager |
|
(604) 793-2907 |
|
|
|
|
|
|
|
-Site meeting will be held at 1:30pm on March 13 on site at 47955 Ballam Road |
Information meeting |
|